Our construction works are near fully complete in early August with landscaping and fencing works remaining to be completed. We expect these items to be completed in the next 2 weeks.

Sadly our electricity supply remains not yet connected. We patiently await the local electrical authority to install the kiosk requirement. This is programmed to be undertaken in September.

Upon its successful install we can then commence the works of compliance and certification as we work towards finalising the development, securing the registration of the plan and issue of the individual Certificates of Title. Once titles are issued settlements can proceed.